Talek Health Centre Phase 4 Updates

August 7, 2018

A ceremony was held for the opening of the x-ray room now that it is officially complete

The plaque that is outside of the x-ray room

 

July 24, 2018

The tiles have gone in and with a few small details to go, the x-ray room is complete

 

July 11, 2018

The x-ray room is almost complete, with tiles still needing to go in

The main water source for Talek Clinic

 

October 3, 2017

New paint for the existing Talek Clinic.

 

September 28, 2017

Walls going up.

 

August 18, 2017

Foundation.

 

July 31, 2017

Starting construction.

 

July 21, 2017

Project ground breaking.