Completed : NAIKARRA PRIMARY SCHOOL – Dorm Toilets and Showers

About the Project

One of our initial projects at the school is to build new toilets and showers for the girls’ and boys’ dormitories. All 2,000 students currently use the dorm toilets until new toilets are finished. There will be 14 new toilets and 14 new showers for each dormitory. 

Photos

Boys Dorm Toilets and Showers completed.

Handwashing station completed.

Girls Dorm Toilets completed.

Painting has been completed.

Girls Dormitory toilets and showers have been completed

Boys dormitory toilets and showers nearly completed

Boys dormitory toilets and showers nearly completed

These large tanks will supply water to the school

Hand washing stations completed

Painting completed

 Work nearly completed.

Painting nearly completed

Water harvesting gutters are being installed

Hand washing stations are completed

Dormitory Toilets and Showers being painted.

Water Tower and 10,000 Litre tank for Dorm Showers

Work on the boys dormitory and showers nearly completed

Girls dormitory toilets and showers are completed.

Steel doors being installed on the girls dormitory toilets
roofing work completed and construction continues on the girls dormitory toilets
Steel doors installed and roofing work completed on girls dormitory showers
Work is nearly completed on the boys dormitory showers
Roofing work has started on the Girls Dormitory toilets and showers
Steel doors being fitted on the boys showers
Work is coming along nicely
Work is coming along nicely
Preparing the foundation for the Boys dormitory toilets
Preparing the foundation for the girls dormitory toilets
Work continues on the boys and girls dormitory toilets
Preparing the groundwork for the girls and boys dormitory toilets
Work on the girls shower continues
Work on the boys showers continues
Wall have gone up on the girls showers
Wall have gone up on the boys showers
Ground work continues
Foundation work has started
building materials have been delivered

Quick Facts

Cost: $81,190
Location:  Maasai Mara, Kenya
Start Date: March 2021
Project Manager:  Brian Leavitt

Major Donors

Jack and Joan Hilde